
NT - Longshaw Estate - Drinking Water Supply Work
- gilesbertenshaw
- 4 days ago
- 3 min read
Project: Longshaw Drinking Water Reservoir – Emergency Repairs and System Upgrade
The Problem
The 24,000-litre, stone-built, in-ground drinking water reservoir at Longshaw was leaking severely, holding only around half of its capacity. Escaping water was flooding the surrounding ground, leading to ground instability and collapse.
The reservoir supplies drinking water to the residents of Longshaw as well as several thousand daily visitors. Maintaining uninterrupted water supply was critical throughout the works.
Previous short-term solutions relied on daily water tanker deliveries, which were expensive, logistically difficult, and limited to a maximum of 24–48 hours.
The Challenge
We were originally tasked with repointing the stone reservoir. However, the requirement to guarantee continuous water supply — combined with restricted access, historic construction methods, and legacy defects from previous works — turned what appeared to be a simple repair into a complex civil engineering project.
The reservoir is located within woodland adjacent to the moors, accessible only by a narrow footpath crossing several small stone bridges. Since the original tank installation in the 1980s, surrounding trees and rhododendrons had expanded significantly, making access extremely difficult.
Our Solution – Temporary Bypass and Supply Continuity
To eliminate reliance on water tankers, we designed and installed a temporary bypass system using the existing pipe network.
Water was diverted through the woodland and connected into the system via a fire hydrant. From there, we installed a new 10,000-litre storage tank, plumbed directly into the filter room and connected to the extensive filtration system, complete with overflow provision.
This system maintained full water supply and pressure throughout the project, allowing the reservoir to be fully drained and repaired without service disruption.
Scope of Works (6-Week Programme)
As the project progressed, significant hidden defects were uncovered, expanding the scope to include:
Repointing of the large stone reservoir blocks using specialist lime and Roman cement mortar
Repair and refurbishment of the timber gazebo, including roof repairs where rot was present
Resetting and repointing of the reservoir coping stones
Installation of a new overflow and controlled discharge into the adjacent stream
Construction of a new, fully accessible valve chamber with upgraded pipework and valve extensions
Installation of a new 8” land drain to replace a blocked perforated system
Repair and sealing of the incoming spring silt trap
Clearance of self-seeded trees and invasive rhododendrons to restore safe access
New pipework from the silt trap to the tank, including a secondary valve chamber
Installation of a new reservoir exit penetration with 90mm HDPE electrofusion-welded pipework
Rationalisation and logical reconfiguration of pipework and valves
Key Discoveries and Remedial Works
Previous works carried out in 2007 by a specialist water contractor were found to be a major contributor to the failure:
An unsuitable plastic manhole system had been installed, cut into, and structurally compromised
The valve chamber was undersized, too deep, and unsafe to access
The tank stop valve was unusable, positioned directly beneath the overflow pipe
The original puddle clay bund had been removed and replaced with weak concrete, allowing water to escape freely
Excavation revealed collapsed chambers, silt ingress, corroded cast iron pipework, and a chaotic arrangement of buried connections.
Engineering Solutions Implemented
Removal of failed concrete and reinstatement of a puddle clay bund, enhanced with bentonite clay
Installation of a new 2.4m deep concrete valve chamber, allowing safe access and long-term maintenance
Relocation of the overflow away from the valve chamber
Installation of valve extenders and brackets for ground-level operation
Creation of a new tank penetration with HDPE pipework sealed using rubber seals and non-shrink underwater grout
New land drainage around the chamber connected to a nearby stream
Replacement of historic perforated drains with new 225mm twin-wall drainage
Repair of the incoming silt trap, including replacement of failed connections with polyfusion-welded joints
Careful pipe bedding and consolidated backfill to accommodate ground movement
The works required progressive escalation of plant, from a 1.5-ton excavator to 3-ton and 6-ton machines, along with multiple dumpers, a 3” pump, and trench sheeting for deep excavations.
Completion and Outcome
The reservoir now holds its full 24,000-litre capacity, with water correctly overflowing to the adjacent streams rather than saturating surrounding ground. All systems are sealed, accessible, and functioning as intended.
To future-proof the installation, we produced a comprehensive work instruction and valve operation manual for National Trust maintenance staff, detailing system layout, valve locations, and operational procedures.
What began as a simple repointing task evolved into a full civil engineering project — successfully delivered using our in-house machinery, expertise, and problem-solving capability.
Another complex project completed safely, efficiently, and to a long-term standard.




















































































































Comments